Hi, please can someone help me:
I inserted some columns using formulas to calculate specific parameters useful for my plan.
For example in my work is important to understand eur/kilos for a project of steel manufacturing, I put in formula “cost/number” and it works correctly.
I made the same for another parameter which is productivity kilos/hours manufactured, I used a number/duration and it works but I don’t understand which number Project is calculating for to me.
Perhaps I don’t understand the exact meaning of the column “Duration”?
Thanks in advance for your support
Gian, try thinking of duration in minutes by default in a formula and see if that help understand your results. Please respond with what you figure out. Thanks…