Loading...
Quick Links

custom fields with formulas

Home Forums Discussion custom fields with formulas

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #402199 Reply
    gian luca
    Guest

    Hi, please can someone help me:
    I inserted some columns using formulas to calculate specific parameters useful for my plan.
    For example in my work is important to understand eur/kilos for a project of steel manufacturing, I put in formula “cost/number” and it works correctly.
    I made the same for another parameter which is productivity kilos/hours manufactured, I used a number/duration and it works but I don’t understand which number Project is calculating for to me.
    Perhaps I don’t understand the exact meaning of the column “Duration”?
    Thanks in advance for your support

    Gian Luca

    #402208 Reply
    Larry Christofaro
    Participant

    Gian, try thinking of duration in minutes by default in a formula and see if that help understand your results. Please respond with what you figure out. Thanks…

    #402215 Reply
    Gian Luca
    Guest

    Yes! you’re right! The software shows into the cells “Hours” but the calculation works with “minutes” by default.
    Thanks
    Gian Luca

    #402216 Reply
    Larry Christofaro
    Participant

    You are very welcome, and glad it helped…

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: Reply #402208 in custom fields with formulas
Your information: