Home Forums Discussion Custom view

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #418318 Reply
    Ahmed Hafez
    Guest

    Hello,
    I would like to be able to create a filter or a customized view of certain tasks, certain selected tasks to show for the project. And not just milestones or summary tasks.
    Just certain tasks of my choosing.

    Thank you.

    #418320 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Ahmed, you’ll need to setup a custom field or flag and then filter on the value of that field. Hope that helps…

    #418321 Reply
    Ahmed Hafez
    Guest

    Thanks Larry,
    Illustrate a little bit please.
    Let’s say, I have the following tasks:
    Mobilization
    Tree clearing
    Foundation
    structure install
    finishing
    commissioning

    and I want to have a filter to only see Mobilization, Foundation and commissioning. and not the other tasks.

    #418322 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    OK, create a custom flag field…call it Key Task or whatever makes sense. Then set the tasks you want to view with the Key Task custom flag set to Yes. Then create a filter that displays Key Task=Yes. If that’s still confusing then you might want to learn a bit about custom fields and filters. These are fairly basic Project functions and there are a lot of information online, including MPUG archive articles, that describe the functionality in detail. Hope that helps…

    #418323 Reply
    Ahmed Hafez
    Guest

    Thanks a lot for the quick response Larry.

    Yes, this clear, the only problem is that the filer criteria are all pre-set, like, starts before, over-allocates, delayed…. etc, what I want is to pick and choose certain tasks, just select tasks, regardless of their schedule or budget or resource status.

    #418324 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    You need to create a new filter that conditions specifically on that flag, and then apply that filter to your view. Lots of articles in MPUG about creating a new filter.

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: Custom view
Your information:




11 + = 16