Home Forums Discussion Do you want to know how to properly remove subplans from a Master plan?

This topic contains 11 replies, has 3 voices, and was last updated by  Mary 2 months, 1 week ago.

Viewing 12 posts - 1 through 12 (of 12 total)
  • Author
    Posts
  • #24678 Reply

    Joseph Yin
    Participant

    For sometimes now, if one simply deletes the sub-projects from a master plan, you will find that the deleted sub-projects’ type remains “Project (sub-project)” and fails to be reverted back to “Project”.

    Recently, I came across the following solution on how to properly remove sub-projects from a master plan and the sub-projects’ type get set back to “Project” again.

    To properly remove subproject plans from an existing Master plan, please follow the steps below:

    1)Open the master project
    2)Select the subproject and right mouse click on “Information” to open the Information window

    3)In the Information window, select the “Advanced” tab

    4)On the Advanced tab, deselect the checkbox “Link to project” and click “OK”

    5)When prompted to save changes to the subproject, click “Yes”

    6)Select the subproject row and delete the row

    7)When prompted, select the “Continue – Delete <your subproject name> and it’s subtasks” choice and click “OK”.

    8)Verify that the subproject row is removed from the Master project plan

    9)Repeat Step 2 to 8 to remove other subproject plans as needed

    10)Once the subproject removals are complete, Save/Publish/Check-in the Master project plan

    11)Open the subproject plan(s)

    12)Save/Publish/Check-in the subproject plan(s)

    Hope this helps and Enjoy.

    #24860 Reply
    Sai Prasad
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    I didn’t know that deleting of sub projects is not so simple. Thanks for sharing this tip. Quite useful, Sai

    #27166 Reply

    Abhishek Kumar

    Thank you for excellent explanation !

    #250953 Reply

    Brad Johanson SM&A

    I have already deleted the 2013 Server master project and the subprojects are still identified as subprojects. Any ideas how to unlink them when you cannot go into the delted master and unattach them?

    #313701 Reply

    Hunter

    How do you correctly unlink a subproject where you have already simply deleted the line item from the master plan? Therefore I cannot right-click the subproject as it is not there.

    #328638 Reply

    Alexei Tchikoulaev

    Brad, publishing the Project from MS Project will do the trick and update the Project Type field in the Server from ‘Sub Project’ to ‘Project’.

    When you delete Master Projects from server, the related Sub Projects remain with this classification in the Project Type field. And publishing in PWA is useless in this case.

    Hunter, you can skip steps 2) to 5). They do represent a more proper way, but in most cases deleting the Sub Project line and then Publishing works fine.

    Alexei

    #359590 Reply

    Danny Spitz

    I have followed the instructions above but cannot delete the sub projects once de-linked as they have actuals booked to them? After publishing and checking in the project still appear as sub projects. Any suggestions?

    #393465 Reply

    Efthimios

    Is resource pool (Master plan serves as resource pool as well) affected by the removal of subprojects? I don’t need finished subprojects in Master but I don’t want to lose recorded work.

    #410319 Reply

    MJB

    I have been struggling with this issue for hours! Thank you. You saved the day

    #411385 Reply

    Benza

    Excellent explanation. You’re GREAT !
    Blame on Microsoft for not having given documentation on this fundamental issue.
    It would be useful to explain how to unlink a Project from a Resource Pool in a correct manner.

    #412283 Reply

    Mary Taylor

    Please list ways to remove a subproject in Project Center without actually deleting it

    #412284 Reply

    Mary

    What are ways to remove a subproject in Project Center without actually deleting it

Viewing 12 posts - 1 through 12 (of 12 total)
Reply To: Do you want to know how to properly remove subplans from a Master plan?
Your information:




35 − = 27