duplication of a repeating series of tasks

Home Forums Microsoft Project Discussion Forum duplication of a repeating series of tasks

Viewing 0 reply threads
  • Author
    Posts
    • #321781
      Arne Gronningsater
      Guest

      I have a schedule where the work flow on one building is repeated in 7 subsequent and similar buildings. How do I copy and paste such that cell values (task predecessors) are relative and not absolute, i.e. that they are in relationship to the building they are in and not the first building?
      Thanks,
      Arne