Duration and Calendat Days Length Issue

Home Forums Discussion Forum Duration and Calendat Days Length Issue

Viewing 1 reply thread
  • Author
    Posts
    • #416293
      Ken Rousseau
      Guest

      I have an issue in that I can put ina duration in whole dys and the calendar day length is extended by one dat almost all the time. I ensured the Working Hours are 8 hours per day, start at 0800 and end at 1700, 40 hrs per week ans 20 days per month. I have tried several combinations of hours per day and start stop times with no change in the discrepancy between duration days and calendar day periods.

    • #416294
      Larry Christofaro
      Participant

      Ken, are you using the same calendar for the project, tasks, and resources? Are you using the standard calendar and have you made any changes (besides day-off exceptions)?

Viewing 1 reply thread
  • You must be logged in to reply to this topic.