Duration days changing when updating % complete

Home Forums Discussion Forum Duration days changing when updating % complete

Viewing 0 reply threads
  • Author
    Posts
    • #124936
      slinkster
      Guest

      I am somewhat new @ project and am just learning so bare with me, team. I am using Project 2010.

      So I base-lined a set of deliverable’s, set the start, current and status date, updated the % comp to 10% on the first task within the deliverable group, and then hit F9 to update the project. When I did that the days on this particular task went from 12 to 14.8 days. I am still learning but was curious why project would push the duration out from 12 to 14.8 days?

      Any help would be appreciated. Thank you!

Viewing 0 reply threads
  • You must be logged in to reply to this topic.