Home › Forums › Discussion Forum › EV and PV in Hours
Tagged: EV, Microsoft Project, PV
Is there an easy way to have MS Project correctly calculate PV and EV in hours? Today we use a custum field that divides PV $ and EV $ by a rate. Problem is I have to have a custom field for the rate. I can’t figure out how to pull the rate off the assinged resource(s) So if there is more than 1 rate assigned to a task I have to average the rate which skews the result.
Simolest way is to use Rate B or another rate set to $1/h. Then all EV $ values are effectively in hours.
EV, PV, AC are in terms of cost.
This is one of fundamental principles. I suggest you use the same. In the long run, you sell based on costs.