Excluding Tasks from Timesheets

Home Forums Discussion Forum Excluding Tasks from Timesheets

Viewing 4 reply threads
  • Author
    Posts
    • #4656

      Within Project Server 2010, is there a way to exclude tasks (or projects) from a users time sheet?  We are using a project plan for production support to  track assignments for capacity/ resource planning purposes.  We do not want to track actual work against these assigned tasks.  Thus, we do not want them to appear in the users time sheet.

      From Member – Kevin Balawender

       

       

    • #4796
      Larry Christofaro
      Participant

      Kevin, there are a few ways to keep tasks from showing up on timesheets.  For individual tasks, you can set the Publish flag to No in MS Project or close the tasks in Close Tasks to Update in server settings.  Projects and resource utilization reporting is not affected by either of these options.  To do this for an entire project, you can set the resource’s Booking Type to Proposed.  This does affect resource utilization only that there are options available to filter resource demand by booking type.  Hope that helps…Larry Christofaro

    • #10282
      Kevin Balawender
      Guest

      Thanks for your help Larry.  This is exactly the info I needed.

    • #11725
      Terry Kneeburg
      Participant

      Kevin, I recently wrote an MPUG article about this topic.  You can find it here https://www.mpug.com/articles/how-to-remove-completed-and-cancelled-projects-and-tasks-from-timesheets-in-project-server/.  All the best, Terry Kneeburg.

    • #343957
      Laneta
      Guest

      wheels car rental stop-start packard dollar rental car suppliers ensure car hire advantage rental car becomes available right car rental uk travel destination often proves long term car rental problems occurring includes various car rental Torino airport deals car

Viewing 4 reply threads
  • You must be logged in to reply to this topic.