Extending project duration

Home Forums Discussion Extending project duration

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #2154
    Avatar photoCommunity
    Keymaster

    Hi there,

    My current project duration is 2 years, but I need to extend it to 2,5 years keeping the same information. Is there a simple way to do it and have all the tasks and sub tasks extended proportionally?

     

    Thanks a lot!

    #6542
    Avatar photoCommunity
    Keymaster

    Sorry there is not a way to do what you need.  What you would need is a function that would add a percentage of work and duration to each task and that doesn’t exisit.   You should manually go through the project and extend the tasks that should be extended.

    #10225
    Avatar photoCommunity
    Keymaster

    Thanks Ellen. That’s not the answer I was expecting, but if that’s the case I’ll have to do it manually.

    #10226
    Avatar photoCommunity
    Keymaster

    You can easily do this with a little help from Excel. Following instructions are on Office 2007.

    (1) Copy only the duration column to Excel. (Gantt chart view-> Right Click on the Duration column heading -> Copy Cell)

    (2) Paste on an Excel sheet.

    (3) Extract the number only. In Excel sheet select Data -> Text to Column -> Delimited -> Delimiter is space

    (4) Apply you formula and get new durations

    (5) Paste new durations back in MS Project.

    Isnt it cool!

    #10227
    Avatar photoCommunity
    Keymaster

    Thanks! That’s a great idea. It didn’t solve all my problems, but it did save me a lot of time a work. Actually, it is very cool!