External Links between Server Instances

Home Forums Discussion Forum External Links between Server Instances

Tagged: 

Viewing 0 reply threads
  • Author
    Posts
    • #29681
      Tom Herrington
      Participant

      I have 2 project server 2010 instances, let’s call them A and B. Instance A has all progress tracking done by timesheet actuals. Instance B tracking is done by percent complete. I would like to have an external predecessor link on a milestone in Instance B tied to a milestone task in Instance A. Is this possible? If so, please show me the syntax required for both project plans.

       

      Both instances run are using Project Server 2010, SP1, patched up to October 2012 CU. We are running on SQL 2012.

       

      Thanks!

Viewing 0 reply threads
  • You must be logged in to reply to this topic.