Hello,
I want to filter activities (assigned and not) that can start now! This activities are those without any predecessor or predecessors are completed.
is it possibile?
saluti, algola
Hi, This is possible by using VBA Macros as you need to loop through the tasks to find if the predecessor is complete or not. I have written a blog post “What are you starting now?” and this will give you detailed steps.
https://bsaiprasad.wordpress.com/2014/10/23/what-are-you-starting-now/