Hi MS Project experts,
I would like to create a filter / view in which it should reflect all tasks with their summary tasks that are less than 100%. All summary tasks that are 100% should be minimized and should not display the child tasks in that view.
All summary with 100% complete should be minimized
All summary less than 100% should display all child tasks.
If somebody can help, to know if a formula can be created for this request or a vba macro and how to do it. Thanks
Thomas John
That is the only task I should have had to do the last couple of days and I also I’m looking for the freezer van rental because I’m in Dubai want to start freezer van business out of the city want to complete a business guide to take over new business.
Is this what you need?
https://imgur.com/VingRdz
The filter is:
(% complete < 100%) OR (% complete = 100% AND summary = yes)
To insert the OR between the two sets of conditions, you simply select the AND/OR column and enter OR and then select the row below to start entering the second set of conditions.