Home › Forums › Microsoft Project Discussion Forum › Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value
Tagged: fixed duration, Microsoft Project Server 2010, task
I have the following situation in our Project Server 2010 env:
Task A (Fixed Duration and Effort Drivin on) assigned to Res A (70%) and Res B (30%). Task has a 5 days duration. Both Res A and B using Standard Calendar. Task Start Date is 4/2/2012 and End Date is 4/6/2012
In PWA, Res A updated his task % completed to 50% and changed the Task Finish Date to date value eariler than 4/6/2012. While Res B has not update anything in PWA.
In PWA, PM views the “Preview Updates” via the approval center, the entries is still showing 0% for % Completed and Finish Date remains unchange – 4/6/2012. PM Approves the update.
In Project client, PM opens the plan the % Completed is still %. However, if PM change the view to Task Usage, he sees % Work Completed for Res A is showing 50%, but Task’s % Completed is still 0%. Res B % Work Completed is still 0 since he has not started on the task.
If both Res A and Res B update the task with % of Completed in PWA, the overall task % Completed will display the lower % Completed value once PM accepts the updates via PWA.
Question – Should the % Completed shows the aggregated % Work Completed by both resources?
Hope this makes sense. Help please.
Sincerely, Joseph
Joseph,
Good explanation of the issue. The first thing to note is that % Complete for the task is not an aggregate of % Work Complete. You also have a % Work Complete for the task which should” be the correct aggregate (assuming both assignments have the same amount of work). % Complete is a percent of actual/remaining time/duration, and % Work Complete is a percent of actual/remaining work.
There still seems to be an issue with % Complete if a resource has any amount of actual work. % Complete should show some amount of completion, even if it doesn’t show a true aggregate of work complete. That may be a bug. I do know that 2010 still has its share of bugs. Have you updated to SP1? That might help.
Hope that helps…
“
Hi Larry:
We are on SP1 with June 2011 CU in our PS 2010 environment. I agreed with you that % COMPLETED should at least have some values since resouces did report progress even if just one of them. The odd part was that if RES A puts 50% and RES B puts 30, then the % COMPLETED will take the lower value. % Work Completed is showing the correct aggregate in my case.
I will try this out with FIXED WORK and FIXED UNIT typed tasks too. Once I completed my testing, I will post to the community on my findings.
Best, Joseph