Has anyone had trouble setting up recurring Labor and Memorial Day’s in 2010?

Home Forums Microsoft Project Discussion Forum Has anyone had trouble setting up recurring Labor and Memorial Day’s in 2010?

Viewing 1 reply thread
  • Author
    Posts
    • #2153
      Community
      Keymaster

      I am getting an error that reads: “The exception conflicts with “Labor Day”, “They both use the same type of exception, Yearly (Positional), and their interval overlaps. Either change the date range or change they type of exception”.

      I have tried changing the number of occurences, etc., but cannot get the recurring feature setup for these holidays. All others worked fine. Any ideas?

    • #10228
      Community
      Keymaster

      What I think it is telling you is that there is a date conflict which you should be able to see in the Exceptions section for the calendar.  You can’t assign the same day twice.  Delete all entries for Labor Day and enter 1 entry to cover the number of years you need.