Having Project Not Include Non-Working Days in Lag Times?

Home Forums Discussion Forum Having Project Not Include Non-Working Days in Lag Times?

Viewing 4 reply threads
  • Author
    Posts
    • #377219
      daniel
      Member

      Project 2010 recognizes that weekend’s aren’t work days. None the less, in the particular case of if I set an activity as lagging 14 days behind another one, I want it to include non-work days within that lagtime (as the deadline of 2 weeks includes work and non-work days). Is there any way to have MS Project recognize that lag time should include all days, not just work days?

    • #377229

      I’m new to MSProject, but I believe (in 2013 at least) you use Edays in the lag time instead of days (Edays refers to Elapsed Days and includes the days off)

      for 2 weeks you could put 14ed or 2ew

    • #377243
      Larry Christofaro
      Participant

      Ken is corect, and available in any version (at least in this century…). The format is 1FS+14 ed (successor to task 1, FS, plus 14 elapsed days).

    • #377678
      daniel
      Member

      Thanks!

    • #415268
      Achini
      Guest

      Can we add elapsed hours in a similar way so that the lag time can be entered in elapsed hours?