Loading...
Quick Links

help!!! I am getting crazy!! –> how can I print the different user calendars??

Home Forums Discussion help!!! I am getting crazy!! –> how can I print the different user calendars??

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #410270 Reply

    Dear All,

    I am getting crazy, I have Microsoft Project 2016 and although I can update the calendar for my 35 resources, I have not found any way to print this “exception”-s of the calendar!!!!

    This is something that is very convenient for me.

    Any help will be really appreciated.

    #410272 Reply
    Larry Christofaro
    Participant

    Julen, I don’t know if someone has a custom or 3rd party solution (which you might want to search for), but I do not believe there is a way to print calendar exceptions using out of box features. Sorry about that…

    #410274 Reply
    Tom Boyle
    Guest

    XER Toolkit does this quite handily, if you can stomach the cost.

    #410275 Reply

    thank you very much! I think I will copy and paste directly this information.

    #410317 Reply

    Julen;
    Here’s something that’s thinking a bit out-of-the-box in terms of an approach, but it may get you the data you want from a different perspective.
    Open a Resource Usage view and collapse the view to only show the summary row for each resource. In the Time Phased data side, right click in the Details column, click detailed styles, and add Work Availability field. This will show, by timescale period the total work availability in that period, regardless of assigned work. You can then change the timescale to be daily or weekly.
    Basically, any weekly Work Availability value less than 40 means time off (vacation or holiday) in that period.
    If needed, you can export that data to an Excel workbook.
    Not exactly in a calendar format you might have been looking for, but the data is there.

    #410318 Reply
    Mike Levine
    Member

    Great recommendation Daryl!

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: Reply #410275 in help!!! I am getting crazy!! –> how can I print the different user calendars??
Your information: