I have a construction schedule with my resources working 7 days a week. Is there a way to create a highlight option for all tasks that take place on a Saturday and/or Sunday?
If you have already modified and used the Standard base calendar as the project calendar, then you can create another calendar, for example, Standard_with_NonWorking and use it to draw nonworking times in the Gantt as explained above.
Thanks Rich! I’ll definitely be using that formula for a flag. One thing I noticed was that it only flags tasks which start and/or finish on the weekend. So for a task which starts on Thursday and runs to the following Tuesday, it would go unmarked.
Any ideas on how to capture those? Thanks again for all the help!