How can I highlight days on the time scale with out making them non working days

Home Forums Discussion Forum How can I highlight days on the time scale with out making them non working days

  • This topic has 1 reply, 2 voices, and was last updated 11 years ago by Anonymous.
Viewing 1 reply thread
  • Author
    Posts
    • #113099
      Garry
      Guest

      Hi All

      How can I highlight certain days, as appears with non working days, on the time scale. I would like to highlight certain days + weeks in which certain tasks nee to be competed + it would be of great benifit if I could see that in the gantt.
      thanks a million.

    • #114280
      Anonymous
      Inactive

      Unfortunately your specific item can’t be done. You can setup deadlines to indicate days that certain tasks need to be complete.