    In MSP, is there a way to make a table view that arranges all of the levels into rows and columns rather than an outline? So you’d have all of the lowest level tasks in one column, and then each summary with repeating data on adjacent columns?

    #483399 Reply
    Jerome Odeh
    Participant

    Can you replicate the table in Excel using dummy tasks and share a screenshot, so that we can get an idea of what you have in mind

    #483972 Reply

    I am afraid this isn’t possible in MS Project – each of the columns is an element in the database for that task row (be it a summary, task or milestone) so the concept of displaying as you want wouldn’t work within the database.