I am trying to figure out how to share resources between different team members. Each team member has their own set of projects, so I would like for them to be able to choose resources from the same “pool”, so I can compile all the projects in a Master MS Project file, and evaluate resources accordingly. The issue I am having is my coworkers cannot access the MS Project Resource file that I created.
When they go to Resources > Resource Pool > Share Resources, the resource file does not show up. Does anyone know how to do this?