Hi, I am trying to get a visual report out of MSP 2010. Each time I try it gives me an error telling me that it needs Excel 2007 or greater. I have Excel 2013 loaded, but this does not seem to be getting recognised by MSP2010.
The problem is a mismatch of levels. MSP 2010 will not see Excel 2013. even though the error message is misleading, your Excel is at a higher level than msp.