Home Forums Discussion Inactivating \'In Progress\' Tasks (Project Pro 2016)

Tagged: 

This topic contains 1 reply, has 1 voice, and was last updated by  Dave Murphy 3 days, 17 hours ago.

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #410522 Reply

    Dave Murphy
    Member

    I am using the Pro version. I understand that you cannot inactivate ‘In Progress’ tasks. My problem is the definition of ‘In Progress’. If I change the %Complete to 100% it still sees the task as an ‘In Progress’ one. My understanding was that an ‘In Progress’ task was one where work had commenced but hadn’t yet been completed.
    Any ideas?

    #410523 Reply

    Dave Murphy
    Member

    Ok – I had put in an Actual start date in error, which meant that progress had been recorded on the task and that therefore ~I couldn’t ‘inactivate’ it. forget the question!

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Inactivating \'In Progress\' Tasks (Project Pro 2016)
Your information:




+ 39 = 47