Home › Forums › Discussion Forum › Inactive Tasks in P2010
Tagged: Microsoft Project Server 2010, Tasks
When making tasks inactive, is the related cost excluded from the overall project cost as well? Also, are these inactive tasks still retrievable in previous saved baselines?
Thanks
Hi Angelique,
Welcome to this Microsoft Project forum:)
I don’t have Project Server or Professional, so I can’t give you a direct answer. But why don’t you create a new file, add a few task and costs and try it out to see what happens,
FAQs, companion products and other useful Project information can be seen at this web address: https://project.mvps.org/faqs.htm
Hope this helps – please let us know how you get on 🙂
Mike Glen
MS Project MVP (97-11)
See https://tinyurl.com/2xbhc for my free Project Tutorials
“