Inactive Tasks in P2010

Home Forums Discussion Forum Inactive Tasks in P2010

Viewing 2 reply threads
  • Author
    Posts
    • #5138

      When making tasks inactive, is the related cost excluded from the overall project cost as well? Also, are these inactive tasks still retrievable in previous saved baselines?

       

      Thanks

    • #6819

      Hi Angelique,

      Welcome to this Microsoft Project forum:)

      I don’t have Project Server or Professional, so I can’t give you a direct answer.  But why don’t you create a new file, add a few task and costs and try it out to see what happens,

      FAQs, companion products and other useful Project information can be seen at this web address:  https://project.mvps.org/faqs.htm

      Hope this helps – please let us know how you get on 🙂

      Mike Glen
      MS Project MVP (97-11)
      See https://tinyurl.com/2xbhc for my free Project Tutorials

       

    • #6820
      • Yes, the cost of inactive tasks is excluded from the overall cost.
      • Yes, if you inactivate the task After the the Baseline has been set. If you set a baseline after you Inactivate the task, then Baseline for those inactive tasks is NOT saved.