I have a master project withe 100 activities/tasks with a milestone task of conclusion.
Later i insert a small subproject (5 tasks)
I would like to have dependencies between the last tak of my master project and my subproject summary task.
Then if i track the tasks of master project will have automatically inpact on the subproject inserted.
Other way How can i constraint (start and finish) the subproject with the master project?
Carlos –
Insert the sub-project, then create the dependency links between the master project’s tasks and the sub-project’s tasks
Ideally, maintain the sub-project as linked, to the master project (make updates to the linked version of the sub-project); otherwise, the links may go away if you delete/re-add a modified sub-project.
To create the link:
1) Select the predecessor task
2) Hold the CTRL key
3) Select the successor task and release the CTRL key
4) Press the “link the selected tasks button” key (Ctrl + F2) in the Task Menu.