Inserting Task/Milestone as predecessor into middle of a task

Home Forums Discussion Forum Inserting Task/Milestone as predecessor into middle of a task

Viewing 1 reply thread
  • Author
    Posts
    • #415825
      MSP newbie
      Guest

      I’m fairly new to the Project and I was wondering if there is way to insert a task or milestone as predecessor into middle of a certain task?
      I don’t think splitting a task is an answer…

    • #415829
      Anonymous
      Inactive

      Newbie but not a newbie question. Project provides a couple of solutions. You can adjust when the successor task starts by using either a number of days or a percent.
      Task 1 with a negative lag of 3 days: 1FS-2 days
      Task 1 at 50% of task 1 duration: 1FS-50%
      Hope that helps…:-)

Viewing 1 reply thread
  • You must be logged in to reply to this topic.

Get our FREE Microsoft Project Speed Guide: 10 Essential Time Savers