I’m fairly new to the Project and I was wondering if there is way to insert a task or milestone as predecessor into middle of a certain task?
I don’t think splitting a task is an answer…
Newbie but not a newbie question. Project provides a couple of solutions. You can adjust when the successor task starts by using either a number of days or a percent.
Task 1 with a negative lag of 3 days: 1FS-2 days
Task 1 at 50% of task 1 duration: 1FS-50%
Hope that helps…:-)