Linkage for repetitive tasks

Home Forums Microsoft Project Discussion Forum Linkage for repetitive tasks

Viewing 0 reply threads
  • Author
    Posts
    • #473775

      Dear Team,

      I need some guidance on my schedule. We have an existing schedule of 28119 activities which is quite messed up and I am required to fix it up. Out of that, I am concentrating on it part by part – Right now for superstructure there are about 7000 activities. (There are 12 towers – 11 are G+14, and one G+3, in short total of 169 slabs). For each slab cycle, there are 37 activities and predecessor and successor assigned to them will get repeated for all 169 slabs. Is there a way to copy and paste or some other method for a slab that the P & S will get the same way linkage as given for one cycle ? Please help

      Regards,
      Varun.K.Gupta