I would like to link tasks such that:
– C completes when G completes (link C to G line number with FF after it I think)
– A & B complete when C completes
– but their start dates are not adjusted by the links
– and the duration (days) adjust to reflect the start and finish dates
I tried linking the completion of A & B with completion of C but it adjusts the start date to match the days for those tasks even though the days are listed as “days?”.
Any direction would be greatly appreciated.
Regards,
Sorry Chris, hard to follow the issue. If you are wanting the system to adjust the duration based on predecessors / successors, Project doesn’t do that. Project will only move the task. If that’s not the case, please provide additional details.