Home Forums Discussion Make % Complete and Actual Work of a Task independent in Project 2013

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #172030 Reply
    Adam Ma
    Participant

    On Microsoft website http://office.microsoft.com/en-us/project-help/actual-work-fields-HP001023098.aspx, there is the following statement regarding how updating % Complete or Actual Work will cause the other to be re-calculated and how this option can be turned off.

    “By default, Project calculates actual work for assignments based on percent complete values that you enter for tasks. You can turn this setting off in the Project Options dialog box.”

    But I don’t see such an option on the Project Options form (File > Options) anywhere. Under File > Options > Schedule, you can turn off the option “Actual costs are always calculated by Project” to make the Actual Cost independent of % Complete. But turning off that option has no impact on Actual Work, which will still be recalculated every time % Complete is changed.

    Any tips and tricks on how to make % Complete and Actual Work independent of each other as Microsoft indicated we can do?

    Thanks,
    Adam

    #173780 Reply
    Joseph Yin
    Participant

    Hi Adam:

    The option to turnoff is “Updateing Task status updates resource status”. I have not use it personally. Hope this helps

    Best, Joseph Yin
    jyin5168@gmail.com

    #416167 Reply
    Dan Schaeffer
    Guest

    As far as I can tell, ‘Updating Task status updates resource status’ does not uncouple changes to Actual Work from changing % Complete.

    #416221 Reply
    Rod Gill
    Guest

    Hi,

    Use Physical % Complete column if you don’t want actual Work etc to change.

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: Make % Complete and Actual Work of a Task independent in Project 2013
Your information:




8 + 2 =