I have a question regrading the resources.
1.0 How do I assign salary staff irrepect of work load with fixed salary per month?
2.0 if he/she works only 25% for first 3 month and then after 50% for rest of the year, how do I adjust the salary 25% from project for 3 month & remaining month, if he/she had salary of USD 1800 per month?
Hi Suman, welcome to the forum. Best way to think through the problem is to figure out the requirement. Reading your question you could create a monthly task and either use the Fixed Cost task column or create a cost resource. It doesn’t sound like a great solution but works which is key. Hope that helps…