MS Project and JIRA bi-directional integration

Home Forums Discussion Forum MS Project and JIRA bi-directional integration

Viewing 8 reply threads
  • Author
    Posts
    • #480005
      Anonymous
      Inactive

      HI All –

      I have been tasked to find an integration tool (or plugin) that can bi-directionally update tasks in the MS Project file with JIRA and from JIRA back to Project. There may be flexibility to use a different Scrum type software other than JIRA. Does someone know if MS project has this integration with either JIRA or other tool used for Sprints?

      Are there other 3rd party software to accomplish this?

      Thanks in advance for your assistance.

      CB

    • #480006
      Anonymous
      Inactive

      I am aware of Ceptah Bridge and The Connector. If anyone has used these I would appreciate your evaluation on them.

    • #480008

      Hi CB

      One of MPUG’s authors has written an article on the topic that may be an option: https://www.mpug.com/up-and-running-ms-project-and-jira-with-a-bridge/

      Hope this helps! All other suggestions are welcome.

      – Team MPUG

    • #480080
      dan schaeffer
      Participant

      I’m a fan of Ceptah Bridge. I’ve never used “The Connector”. I don’t even recall whether I evaluated The Connector an the time. One of my criteria was that I didn’t want to have to engage with IT or a Jira Admin and the cost of Ceptah was also reasonable enough that I didn’t have to make a huge case for getting it.

    • #480151
      Anonymous
      Inactive

      Thanks Dan for the reply. I have a couple of questions on Ceptah is you could help.

      Does it allow you to Sync multiple JIRA projects to a single MS Project.
      Is there anything about the app that you don’t like?

      Thanks again for your time.

    • #480160
      dan schaeffer
      Participant

      Multiple Jiras into one MSProject eh? That’s a weird one. I can’t imagine that’d be possible but the person to ask is Sergey Gussak, Ceptah Bridge’s author (helpdesk@ceptah.com).

      I think the product is simple and well-designed. I never found it to be buggy. My bigger problem was with my own ignorance of MS Project and Jira – and that was a large learning curve. If you’re not well grounded in both you’ll find the instructions for Ceptah Bridge to be terse and not particularly kind. The best thing to do is work through a bunch of use cases with demo Jira databases and MS Project files until you’re very clear on what you need/want to do. You’re likely to need your Jira admin to craft some custom fields for you as well.

      IMHO Jira/Project/Ceptah are a killer combination letting you stay on top of the complexity of a rapidly shifting software project.

    • #482780
      strobert2
      Participant

      Hello,
      In case you interested in updating actual work from external sources including jira, you can check this
      This is for a dektop version only
      kind regards,
      Stéphane

    • #483441
      Anonymous
      Inactive

      100% Pass Rate Guaranteed PMP certificate without exam in Saudi Arabia Buypmpwithoutexams@yahoo.com | Buy TEF certificate without exam Saudi Arabia | Buy PMP certificate without exam in Saudi Arabia

      https://www.buypmpwithoutexams.com can help you obtain Certifications for every stage of your career.

      PMP Certification Training Course in Saudi Arabia
      PMP Certification in Saudi Arabia is a great start for the professionals to acquire and get certified in PMP. There are a lot of changes in the PMP course topics in the latest 6th edition of the PMP certification course. If you are an aspiring project manager or looking for PMP online training certification in project management, then the PMP course in Saudi Arabia is the right choice to celebrate the success of project management in your career. PMP Training in Saudi Arabia will empower you with all the required tools and techniques.

    • #483892
      Amy Crook
      Guest

      The Average score in the Rice Purity test is 72 considering only those students who said that they study at Rice University.
      This score can vary for other universities. If you want to know more about this rice purity quiz, steps to play, and what do your purity score means, read this post further.

Viewing 8 reply threads
  • You must be logged in to reply to this topic.