Home › Forums › Discussion Forum › MS Project Enterprise 2010
Tagged: Microsoft Project 2010
I had a project task in MS Project Enterprise 2010 with resources logging time and everything was good until a few days ago I noticed the end date automatically switched to 1984 from 7/25/13. Has anyone ever seen this before? If so please help.
If you have brought in tasks from another project or are merging projects, then the start date from the other project could have overridden your start date or MSP could have a conflict and given a default date. This has happened to me when I brought in tasks from another project, but when I reset the dates, the merged tasks fell in line.