MSP 2010 Reporting Tool?

Home Forums Microsoft Project Discussion Forum MSP 2010 Reporting Tool?

Viewing 1 reply thread
  • Author
    Posts
    • #5279
      Community
      Keymaster

      We are using MSP2010 and Sharepoint server, we have over two hundred projects on the server, what is the best reporting tool from MSP to query/report selected project information, for certain periods of time? Example: I want to pull project in Design Phase for a fiscal year. Any suggestions, it seems like SQL Reporting Services may be the best selection??

    • #9696
      Community
      Keymaster

      You probably already have all of the tools that you need. The Business Intelligence Center in PS2010 will allow you to build the reports that you need, and can leverage Excel Services, Visio Services, PerformancePoint, and SSRS.

      Here’s an article to get you started:

      https://technet.microsoft.com/en-us/library/ee662106.aspx