I have several projects set up to feed a master schedule and we are using Project Professional 2010 (not using a server.) We are using a file share on our intranet and multiple people are accessing the files.
My question is, if someone has one of the projects open, can I roll up any changes I make in a read-only version of the project into the actual project once the person gets out of it and I can get access to the original? Ideally, it would just populate the updated-and-now available project file with any changes I made in the read-only version I was forced to work with since I was locked out of the original.
I know this can be done if you use a server set up but we are not. We simply have it on a file share.