    Hello
    I am new to this group. I am working on a large highway & bridge construction project and would like to get a sample template for my project with alot of the activities and WBS structure already entered into the project.  Any help in finding this would be appreciated.
    John Mack, PE
    #10101 Reply
    Community
    Community
    Keymaster

    was available, I would never, ever, use it! To do so would be courting disaster (and quite likely a court action). The only place to start is key deliverables from your contract then entering key components from your drawings and work down from there. For a project like this, you need a professional scheduler to at least get you set up.

    #410704 Reply

    Dey sukh

    <I need a format for highway construction

    #414547 Reply

    solomon

    i was looking for a t-girder or any bridge construction schedule template