Need an MS Project Template for a large Highway & Bridge project

Home Forums Discussion Forum Need an MS Project Template for a large Highway & Bridge project

Viewing 3 reply threads
  • Author
    Posts
    • #4992
      Marcus Peterson
      Keymaster
      Hello
      I am new to this group. I am working on a large highway & bridge construction project and would like to get a sample template for my project with alot of the activities and WBS structure already entered into the project.  Any help in finding this would be appreciated.
      John Mack, PE
    • #10101
      Marcus Peterson
      Keymaster

      was available, I would never, ever, use it! To do so would be courting disaster (and quite likely a court action). The only place to start is key deliverables from your contract then entering key components from your drawings and work down from there. For a project like this, you need a professional scheduler to at least get you set up.

    • #410704
      Dey sukh
      Guest

      <I need a format for highway construction

    • #414547
      solomon
      Guest

      i was looking for a t-girder or any bridge construction schedule template