need to have different calendars in same Project Server Project

Home Forums Discussion Forum need to have different calendars in same Project Server Project

Viewing 1 reply thread
  • Author
    Posts
    • #5000
      I have a team that is overseas and has different working days than we do (S-TH).
      I created a sub-project that calculated everything just as I wanted and it immediately stopped working correctly when I linked it into the Master with the standard calendar.
      Does anyone know how to accomodate this?  I’m using project server 2010 and am not allowed to have task or resource level calendars.
      THANKS!
    • #6434
      With no tak or reource calendars teh only way is to have a different base calendar for your project. Don’t use Standard for both.
      If the overseas country uses d/m/yy date format make sure all reports use a d mmm yy or mmm d yy format to avoid confusion.
Viewing 1 reply thread
  • You must be logged in to reply to this topic.