Home Forums Discussion Not updating Remaining work in Timesheet after Actuals entered

This topic contains 1 reply, has 2 voices, and was last updated by Sai Prasad Sai Prasad 2 months, 3 weeks ago.

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #415015 Reply

    Beth Lee

    When users enter their actual hours work in the timesheet and save the entry the system is not updating the remaining or actual hours worked in the table. Also, it will not allow users to adjust the remaining hours of work in the table.

    Task Settings and Display set to Actual work done and work remaining; Resources should report their hours worked every day.

    Timesheet settings and defaults set to Current task assignments; Default timesheet tracking units are Days; Default timesheet units is hours; Allow future time reporting.

    Any suggestions on what might be causing this issue and how to resolve?

    #415023 Reply
    Sai Prasad
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Hi Beth, Is single entry mode in Timesheet settings and Defaults in PWA settings ON? Only if this is ON, Task progress entered in Timesheet page will be synchronized against the tasks in Task page and vice versa.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Not updating Remaining work in Timesheet after Actuals entered