    • #5179
      Avatar photoCommunity
      Keymaster

      I’m using a pivot table report that was pulling a particular task name, start date, etc over mulitple projects. while inspecting the data in the report to the actual project schedule, some dates do not match up to the task. I have refreshed the data from the pivot table, but it doesn’t seem to correct the error. It is not on all the projects, just some. Any ideas?

    • #6882
      Avatar photoCommunity
      Keymaster

      Joe,

      Is your Pivot tabe an OLAP Cube based? if yes, then you will only see the data as of last build (typically once every night). Check your cube build settings.