Planned Administrative Time – MSP Server 2010

Home Forums Discussion Forum Planned Administrative Time – MSP Server 2010

Viewing 1 reply thread
  • Author
    Posts
    • #5034
      Sathia Siddart
      Keymaster

      How do you report planned administrative time in Project Server 2010?  Back in EPM2007, we used a “Plan Administrative Time” menu selection, but I don’t see that anymore.  Am I missing something simple that’s in plain sight?

    • #6589
      Sathia Siddart
      Keymaster

      Its slightly different from 2007…Here are the steps.

      • Click on Timesheet link from Quick Launch on the left.
      • Go to the timesheet period that you want to plan administrative time Time for by clicking on select period.
      • Make sure that Planned line is displayed. If not, Insert the Planned” line by checking the box on the ribbon
      • Input hours on the Planned line for the administrative time that you are planning.
      • Select the task by clicking on checkbox beside the name of the task
      • Click on  Send Status >>  Selected Tasks.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.