Porting JIRA data into Project 2013; tasks to show Est Hours, Hours Worked, etc

Home Forums Discussion Forum Porting JIRA data into Project 2013; tasks to show Est Hours, Hours Worked, etc

Viewing 0 reply threads
  • Author
    Posts
    • #98126
      Marc Cadden
      Participant

      My client uses JIRA to track stories and sub-tasks, but I find JIRA reporting lacking. My consulting agency requires status reporting using MS Project 2013. I have added columns for Work, Duration, and Remaining Duration but it appears there is not relationship in MS Project between the values. That is, I set Duration to Fixed Duration in Hours, log Hours under Work, but Remaining Duration does not change. I feel I am missing something basic, but navigating help has not resolved my question.
      Any help out there.

Viewing 0 reply threads
  • You must be logged in to reply to this topic.