Home Forums Discussion Problem with MS Project 2016 -cannot move tasks

This topic contains 0 replies, has 1 voice, and was last updated by  amy schneider 1 week ago.

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #415318 Reply

    I have a virtual machine instance of MS Project 16 running on a Windows 10 instance on my MAC.
    I have set up the gantt chart with fields for planned start and planned finish, and actual start and actual finish.
    When I created the tasks they were manual only. Then I switched to automatic and added a planned start and finish date and then updated the percent work complete to 100% the actual start and finish still remain NA. Why?

Viewing 1 post (of 1 total)
Reply To: Problem with MS Project 2016 -cannot move tasks
Your information:




39 + = 47