Problem with MS Project 2016 -cannot move tasks

Home Forums Discussion Forum Problem with MS Project 2016 -cannot move tasks

Viewing 0 reply threads
  • Author
    Posts
    • #415318
      amy schneider
      Participant

      I have a virtual machine instance of MS Project 16 running on a Windows 10 instance on my MAC.
      I have set up the gantt chart with fields for planned start and planned finish, and actual start and actual finish.
      When I created the tasks they were manual only. Then I switched to automatic and added a planned start and finish date and then updated the percent work complete to 100% the actual start and finish still remain NA. Why?

Viewing 0 reply threads
  • You must be logged in to reply to this topic.