Progress lines & summary tasks

Home Forums Microsoft Project Discussion Forum Progress lines & summary tasks

  • This topic has 0 replies, 1 voice, and was last updated 5 years ago by Adam Glover.
Viewing 0 reply threads
  • Author
    Posts
    • #413495
      Adam Glover
      Guest

      Hi All,

      I have a summary task that has 4no subtasks and the progress for all subtasks is 0%.

      When I show the progress (drop) line, the progress point moves to the end of the subtask, as though it were 100% complete. If I change the progress of 1no subtask to 1% the progress point moves to where I’d expect it.

      Does anyone have any thoughts as to what is happening here?

      Many thanks in advance

      Adam

Viewing 0 reply threads
  • You must be logged in to reply to this topic.