Project Server 2010 – Customize Task display in PWA when drill into Project schedule details

Home Forums Discussion Forum Project Server 2010 – Customize Task display in PWA when drill into Project schedule details

Viewing 1 reply thread
  • Author
    Posts
    • #4903
      Hi there:
      Anyone knows how to customize task view to display in PWA when viewing project schedule?.  Here is our use case:
      1) We have a project where tasks are divided into 2 teams (I.E Designer and Programmer)
      2) We want to create a view in PWA to color code the tasks based by team (i.e. Designer’s task in Orange and Programmer’s task in Light Yellow)
      The goal is to achieve a clear overview for the users when viewing the project via PWA and able to identify the tasks more efficiently.
      Sincerely, Joseph C. Yin
      Qualcomm Incorporated.
    • #6171
      No Sorry, Joe. No way as far as I know.
      What you could do is use the resource team field to sort or have a custom filed with task type and sort/filter/group on that field to diferentuate.
      The other option (bit of a cludge) run up a SRSS report that was coloured in the fashion you want and display in the RS viewer Webpart in the PWA.
      Sorry no better news mate.
      Simon Newton