Project Server 2013 Portfolio Analysis Analyze Cost – Changing the cost value

Home Forums Microsoft Project Discussion Forum Project Server 2013 Portfolio Analysis Analyze Cost – Changing the cost value

Viewing 0 reply threads
  • Author
    Posts
    • #417719
      Michael Kurth
      Participant

      In the MS Project 2013 Managing Projects and Portfolios guide the Portfolio Analysis Analyze Cost section example discusses a change in value of the PMO High Estimate cost variable. I have seen other texts with a similar example but I cannot figure out how the value is changed? The PMO High Estimate value looks to be a sum of this field from projects included in the analysis and given the analysis is a snapshot of project values at the time it is created, it does not appear the way to change it is by altering the value in the individual projects? Can someone shed some light on how this value is changed?

Viewing 0 reply threads
  • You must be logged in to reply to this topic.