I have a project that I am working on, Can you please let me know how to change the project summary task dates? Is this possible to do?
When I go to summary task information the dates are blacked out
Hi Rosie! Those are calculated from the tasks below, within the summary, and should not be changed. They can be hidden, but manually typing within those cells will mess things up for an automatically-scheduled sheet.