Loading...
Quick Links

Project timeline view ( Baseline vs estimated timeline)

Home Forums Discussion Project timeline view ( Baseline vs estimated timeline)

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #416041
    Madhu
    Guest

    Hi All,

    Is it possible to create a timeline view in MS project with Baseline time viewed at the top and estimated timeline ( based on actual start and finish) displayed at the bottom. This will help the viewer to understand where the project is against the planned finish and where the project is headed?

    #416043
    Larry Christofaro
    Participant

    Madhu, unfortunately no…at least not with current versions. You can export data to Visio which should let you create what you are looking for, but I don’t do a lot with Visio and can’t be of much help. Good luck…

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.