Home › Forums › Microsoft Project Discussion Forum › Projects
some of my task do not have the correct duration calculated not all of them does anyone know what is causing this?
Hi Bill, that can be due to calendar changes. Are you using multiple calendars for tasks/resources?
Do you have resources assigned to summary tasks? They should only be assigned tot he lowest levels.
Remember Me
Please enter your username or email address. You will receive a link to create a new password via email.